Battlefield Road/Route 65 Interchange Reconstruction Project Update Dec 22
	
	
	
	
	
	
	
	
	
	December 18, 2014 09:31 AM
	Battlefield Road/Route 65 Interchange Reconstruction Project
	Update for Week of Dec. 22, 2014
	- 
		Short-term traffic stops on the northbound on ramp and southbound off ramp
 
	- 
		No work on project between noon on Christmas Eve and Monday, Dec. 29
 
	Work Scheduled: 
	- 
		Breaking rock ‘round the clock and excavating dirt along the northbound on ramp (northeast ramp)
 
	- 
		Hauling rock and dirt from northbound on ramp (northeast ramp) to storage areas including southbound Route 65 for future auxiliary lane
 
	Traffic Impacts: 
	- 
		Short-term traffic stops on northbound on ramp (northeast ramp) and southbound off ramp (northwest ramp)
 
	- 
		Right shoulder closed along southbound Route 65 at times
 
	- 
		No lane closings planned on Battlefield Road or on Route 65
 
	- 
		Be alert for trucks entering and leaving work areas
 
	(Weather or construction delays could alter the work schedule.)
	Project Summary:
	- 
		Replace Battlefield Road bridge over Route 65
 
	- 
		Convert interchange to a Diverging Diamond configuration
 
	- 
		Build northbound and southbound auxiliary lanes on Route 65 to connect Sunshine Street and Battlefield Road ramps
 
	- 
		Install new traffic signal at Battlefield Road and Woodstock Avenue
 
	Project information with live camera view
	Prime Contractor: Hartman and Company, Inc., Springfield
	Completion Date: September 2015
	Total Project Cost: $12.5 million.
	Partnership Project: City of Springfield, Greene County, Ozarks Transportation Organization, Jack Henry & Associates, Justice Jewelers and McLean Enterprises, Inc.
	 